Posted by Chester Morton / Wednesday, 22 June 2016 / No comments
Cost Variance
Cost variances can be divided into four categories.
- Direct Material Cost Variance
- Direct Labour Cost Variance
- Variable Overhead Cost Variance
- Fixed Overhead Cost Variance
Variances occur generally as a result of the following
reasons:
- Poor budgeting
- Poor measurement or recording
- Operational factors such as production efficiency, supervision, etc.
- Random factors such as price level changes, political factors, technological factors, etc.
A.
Direct
Material Cost Variance: It is the difference between the standard cost of
direct materials allowed or expected to be used for a given output and the
actual cost of direct materials used. That is,
Direct Material Cost Variance =
(Standard Direct Material Cost) – (Actual Direct Material Cost)
Standard cost of direct material
expected to be used for a given output produced can be calculated as shown;
- Standard cost = (Actual output produced) × (standard materials allowed per unit of actual output) × (standard price of material)
- Standard materials allowed for a given output = (Actual output produced)× (Standard materials allowed per unit of output)
- Standard materials allowed are also called Standard Quantity.
EXAMPLE 1
Calculate the standard materials allowed and the standard
cost from the following data in respect of Alex, production worker.
Actual output produced in the past week 100 bottles
Standard materials allowed per bottle produced 20 litres
Standard price per litre of direct materials used $700
Solution
Note that apart from the output produced, the other results
(20 litres and $700) are expected results. If Alex produced 100 bottles, he
would be expected to use 2,000 litres (i.e. 20×100) of the raw materials. Thus standard
direct materials allowed or expected = Actual output × Standard materials
allowed per bottle
= 100 × 20
= 2,000 litres
Standard cost of direct materials = Standard direct
materials allowed × Standard price per litre = 2,000 × 700 = $1,400,000
Direct Material Cost Variance can be sub-divided into:
1.
Direct
Material Price Variance: It is the difference between the standard price
and the actual price for the actual quantity of materials used. That is,
Direct Material Price Variance =
(Standard Price –Actual Price) × Actual Direct Material Used
- Standard price of material is the price expected to be paid for every metre, kilogram, litre, etc of material purchased.
·
Actual
price of material is the price actually paid for every metre, kilogram, litre,
etc of material purchased.
Causes of Material Price Variances
The possible causes are:
i. poor
budgeting;
ii. poor
recording or measurement;
iii. unexpected
price changes;
iv. different
source of supply;
v. alteration
in quantity discounts;
vi. substitution
of a different grade of material;
vii. standard
set at mid-year price leading to favourable price variance in early months and
adverse variance later.
2. Direct Material Usage Variance: It is
the difference between the standard quantity of direct materials allowed for
the actual production and the actual quantity of direct materials used, at
standard purchase price. That is,
Direct Material
Usage Variance = (Standard Direct Material Quantity – Actual Direct Material Quantity)
× Standard Price
Causes
of Material Usage Variance
This could be due to:
i.
poor planning;
ii.
poor recording or measurement;
iii.
level of supervision;
iv.
usage of faulty machine or plant;
v.
higher/lower incidence of scrap;
vi.
alteration to product design;
vii.
substitution of a different grade of material;
viii.
substitution of a different grade of employees.
B. Direct Labour Cost Variance: It is the difference between the standard direct labour cost and the actual direct labour cost incurred for the actual production achieved. That is,
Direct Labour Cost Variance =
(Standard Direct Labour Cost) – (Actual Direct Labour Cost)
Standard cost of direct labour
expected to be incurred for a given output produced can be calculated as shown;
Standard cost = Standard
hours allowed × Standard rate per hour
Standard hours allowed = Actual
output produced × Standard direct labour hours allowed per unit
Following from the example above in respect of Alex,
assuming
Actual output produced in the past week was still 100 bottles
Direct labour hour allowed per bottle is 2
hours
Standard direct labour rate per hour is $8,000
Solution
If Alex produced 100 bottles, he would be expected to use
200 (i.e. 20×100) of direct labour hours. That is,
Standard direct labour hours expected/allowed = Actual
output × Standard direct labour hours per bottle
= 100 × 2
= 200 hours
Standard direct labour Cost = Standard direct labour hours
allowed × Standard direct labour rate per hour
= 200 × 8,000
= $1,600,000
Direct Labour Cost Variance can
be sub-divided into:
1.
Direct
Labour Rate Variance: It is the difference between the standard and the
actual direct labour hour rate, for the total hours actually worked. That is,
Direct Labour
Rate Variance = (Standard Direct Labour Hour Rate –Actual Direct Labour Hour
Rate) ×
Actual
Direct Labour Hours Worked
- Standard direct labour hour rate is the rate expected to be paid for every direct labour hour worked.
·
Actual direct
labour hour rate is the rate actually paid for every direct labour hour worked.
Causes of Labour Rate Variance
The possible causes are:
i. poor
planning;
ii. poor
recording or measurement;
iii. unexpected
wage award;
iv. overtime
or bonus payments different from plan;
v. substitution
of a different grade of labour.
2.
Direct
Labour Efficiency Variance: It is the difference between the standard hours
required for the actual production achieved and the hours actually worked,
valued at standard direct labour hour rate. That is,
Direct Labour Rate Variance = (Standard
Direct Labour Hours – Actual Direct Labour Hours) ×
Standard Direct Labour Hour Rate
Causes of Labour
Efficiency Variance
The possible causes are:
i. poor
planning;
ii. poor
recording or measurement;
iii. level
of supervision;
iv. working
conditions including workshop organisation;
v. consequences
of the learning effect;
vi. introduction
of incentive scheme or staff training;
vii. efficiency
of machine;
viii.
substitution of a different grade of labour.
Where the hours recorded or clocked by employees are more
than the actual hours worked, idle time is recorded. This will lead to idle time variance. This is calculated
by multiplying the idle hours by the standard labour rate thus,
Idle Time Variance = Idle hours × Standard labour rate
Idle time variance is always adverse.
EXERCISE 1
Joy Company manufactures one standard product. The standard
cost of producing one unit is calculated as follows: $
Materials:
20 kg @ $300 per kg 6,000
Labour: 6
hours @ $250 per hour 1,500
7,500
Production
overheads 2,500
10,000
For the month of October 1994, 800 units were produced. A
total of 14,400 kg of materials were bought and used at a total cost of $5,040,000.
A total of $1,120,000 was paid as wages for the 4,000 labour hours used in the
month.
You are required to calculate:
(a) Total Material Cost Variance analysed into Price
Variance and Usage Variance;
(b) Total Labour Cost Variance analysed into Rate Variance
and Efficiency Variance.
EXERCISE 2
An extract of a standard cost card for one tonne of a
product called Zain is as below:
$
Direct material: 50kg @ $100 per kg 5,000
Direct
labour: 10 hours @ $800 per hour 8,000
During April 2009, 70 tonnes of Zain was produced. Other
costs were:
Direct
material: 3,200kg costing $384,000
Direct labour:
800 hours costing $608,000.
You are required to calculate:
(a) direct material price variance;
(b) direct material usage variance;
(c) total direct material cost variance;
(d) total direct labour cost variance;
(e) direct labour rate variance;
(f) direct labour efficiency
variance.
C. Fixed Production Overhead Variances
The overall
fixed overhead variance is the fixed
overhead total variance. It is the difference between fixed overhead
incurred (actual fixed overhead) and fixed overhead absorbed. This is the same
as the fixed overhead under- or over-absorbed.
It is
calculated as;
Fixed
overhead total variance = Fixed overhead absorbed – Fixed overhead incurred
Fixed overhead
absorbed is calculated as;
Fixed overhead
absorbed = Actual output × Standard hours per unit × Fixed overhead absorption
rate per hour
Fixed overhead
total variance can be sub-divided into fixed overhead expenditure variance and fixed overhead volume variance.
1. Fixed Overhead Expenditure
Variance: This is the difference
between budgeted fixed overhead expenditure and actual fixed overhead
expenditure. Thus,
Fixed overhead expenditure
variance = Budgeted fixed overhead – Fixed overhead incurred
2. Fixed
Overhead Volume Variance: This is the difference between actual and budgeted
volume of output
multiplied
by the standard fixed overhead absorption rate per unit of output. Thus,
Fixed overhead volume variance = (Actual
output – Budgeted output) Standard fixed overhead rate per unit
It can also be
calculated as;
Fixed overhead
volume variance = (Standard hours – Budgeted hours) Standard fixed overhead
rate per hour
Fixed overhead
volume variance can be sub-divided into fixed overhead volume capacity variance and fixed overhead volume efficiency variance.
a.
Fixed
Overhead Capacity Variance: This is the difference between actual hours
worked and budgeted hours, valued at fixed overhead absorption rate per hour.
i.e. Fixed
overhead capacity variance = (Actual Hours Worked – Budgeted Hours) Fixed
overhead rate
per
hour
b.
Fixed
Overhead Efficiency Variance: This is the difference between standard hours
worked (i.e. hours that actual production should have taken) and actual hours
worked, valued at fixed overhead absorption rate per hour.
i.e. Fixed overhead efficiency
variance =
(Standard Hours of Actual production –
Budgeted Hours) Fixed overhead absorption rate per hour
D. Variable Production Overhead Variances
The behaviour of variable costs,
compared with fixed costs, calls for different techniques when analysing
variable overhead variances. Variable overheads are expected to change with the
level of activity while fixed overheads are expected to remain the same
regardless of the level of production.
1. Variable Overhead Total Variance: This
is the difference between variable overhead absorbed and actual variable
overhead incurred. It can be calculated as below;
Variable overhead total variance = Variable overhead
absorbed – Actual variable overhead incurred
Variable overhead absorbed = Actual output × Standard
hours per unit × Variable overhead absorption rate
per
hour
The variable overhead total variance can be divided
into variable overhead expenditure
and variable overhead efficiency
variances.
a.
Variable
Overhead Expenditure: This is the difference between the variable overhead
that should have been incurred for the actual hours worked (i.e. standard
variable overhead) and the actual variable overhead incurred. That is;
Variable overhead
expenditure variance = Standard variable overhead – Actual variable overhead
Standard variable overhead
= Actual hours worked × Variable overhead absorption rate
b.
Variable
Overhead Efficiency Variance: This is the difference between standard hours
and actual hours worked for the actual output produced, valued at the variable
overhead absorption rate. That is,
Variable overhead
efficiency variance = (Standard hours – Actual hours) Variable overhead
absorption rate
EXERCISE 3
The standard cost card of Beware
Enterprise for product Dragon is shown below:
$
|
||
Direct material
|
(5kg @ $4)
|
20
|
Direct labour
|
(7hours @ $3)
|
21
|
Prime cost
|
41
|
|
Variable overhead
|
(7hours @ $6)
|
42
|
Fixed overhead
|
(5hours @ $8)
|
56
|
Total standard cost
Standard profit
Standard selling price
|
139
11
150
|
|
Budgeted output was
|
13,500 units
|
|
In the course of operating
activities, it was realized that the above standards failed to take certain
factors into consideration which would have made the standard cost card look as
below
$
|
||
Direct material
|
(4kg @ $6)
|
|
Direct labour
|
(6hours @ $4)
|
|
Prime cost
|
||
Variable overhead
|
(9hours @ $8)
|
|
Fixed overhead
|
(8hours @ $5)
|
|
Standard profit
|
25
|
|
Budgeted output was
|
13,500 units
|
|
Required: Calculate
1. (a) direct material price variance; (b) direct material usage variance; (c) total direct material cost variance;
(d) total direct labour cost variance; (e) direct labour rate variance; (f) direct labour efficiency
variance.
(g) Fixed overhead total variance (h) Fixed overhead expenditure variance (i) Fixed overhead volume variance
(k) Fixed overhead capacity variance (l) Fixed overhead
efficiency variance (m) Variable
overhead total variance (n) Variable
overhead expenditure variance (o) Variable overhead efficiency variance. (
p) Total sale Variance
(q) sales volume profit variance (r) sale price variance
2. a. Planning Direct Material cost variance b. Operational Direct material cost
variance c. Planning direct material price variance d. planning direct material
usage variance e. Operating direct material price variance f. Operating material usage variance g. Planning Direct labour cost variance h. Operating direct labour cost variance i.
Planning labour rate variance j. Planning labour efficiency variance k. Operating labour rate variance L. Operating labour efficiency variance
Labels:
PRINCIPLES OF COST ACCOUNTING
Related Posts